PROJECT CONTRACTOR ESTIMATED COST FUNDING COMPLETION DATE
Fill additional potholes on Aspen Way near building 3 Lizell

Contracting

$467 Operating 1/2/15
Lubricate locks at boiler room doors, M-1 through M-25, and replace ten locks Lizell Contracting Hourly Rate Operating

GL “6540”

1/15/15
Discard fan, plastic chairs, and recycle metal desk in maintenance room Lizell

Contracting

$198 Operating 1/23/15
Schedule/confirm oil delivery by Brinker’s mid-cycle – January Continental Property Management N/A N/A 1/29/15
Repaint community entrance sign near building 11 Fisher Sign Services $640 Operating 1/30/15
Chip Christmas trees – Install in woodchip beds LFB Landscaping $675 Operating 1/31/15
2014 financial report – Audit Luft & Company $1,850 Operating 2/4/15