PROJECT | CONTRACTOR | ESTIMATED
COST |
FUNDING | COMPLETION DATE |
Building inspection – Create list of areas to power wash by 3/31/17 | Continental Property Management | N/A | N/A | 9/8/16 |
Mail cover letter and heating system booklet to all unit owners/residents | Continental Property Management | Copying and Mailing | N/A | 9/12/16 |
Removal of leaves/debris from
inside all fenced-in above-ground oil tank locations |
Lizell Contracting | Hourly Rate | Operating
GL “6540” |
9/20/16 |
In-depth tree inspection, create list/map to perform tree pruning/ removal – January 1 – February 28, 2017 | Continental Property Management | N/A | N/A | 9/20/16 |
Improve storm water drainage near ground level patio 5-19 (complete after concrete patio is replaced) | LFB Landscaping | $1,475 | Operating | 9/21/16 |
Concrete sidewalk replacement –
95 locations, 1,349 sq ft |
Unitex | $17,605 | Reserve | 9/30/16 |
Turn on all boilers M-1 to M-25 | Continental Property Management | N/A | N/A | 10/4/16 |