PROJECT CONTRACTOR ESTIMATED COST FUNDING COMPLETION DATE
Inspect attic area above 2-7 and provide recommendation to improve ventilation Eiseman Construction Hourly Rate Operating 2/14/18
Improve storm water drainage at sidewalk at front of 5-7 LFB Landscaping $975 Operating 2/14/18
Improve storm water drainage at  front of 3-5 / 3-6 at sidewalk LFB Landscaping $985 Operating 2/14/18
Improve storm water drainage at sidewalk near 11-17 LFB Landscaping $950 Operating 2/14/18
Remove 139 shrubs and grind stumps at 97 locations LFB Landscaping $5,100 Operating 2/15/18
Schedule/confirm oil delivery by Brinker’s mid-cycle – February Continental

Property

Management

N/A N/A 2/20/18
Replace roof above 4-11 and boiler room M-11 – 375 sq ft Eiseman

Construction

$2,016 Reserve 2/20/18
Mail first notice of annual election meeting to unit owners and exterior building powerwashing letter to entire community Continental Property

Management

Copying/

Mailing

Operating 2/26/18
Removal of leaves/debris/snow from inside all trash enclosure areas Lizell Contracting Hourly Rate Operating 2/28/18
Activate exterior spigots at all boiler rooms Lizell Contracting $464 Operating 2/28/18
Sol-U-Cal lime turf application soil level pH 5.9 TreeEx $778 Operating 3/1/18
Remove fallen ash tree at rear of

8-1

TreeEx $600 Operating 3/6/18