PROJECT CONTRACTOR ESTIMATED COST FUNDING COMPLETION DATE
Clear vegetation at intersection near Pine Run, and at side of buildings 8, 9, 10, and 11 near Pine Run LFB Landscaping $450 Operating 4/2/18
Clean seventy (70) courtyard globe light fixtures Lizell Contracting $1,190

(2017 Price

$1,190)

Operating 4/30/18
Remove 103 Rubbermaid buckets with calcium chloride from designated locations – Store in nearby boiler rooms – Provide list of buckets, lids, and scoops to replace Lizell Contracting $1,386 Operating

GL “6465”

5/4/18
Clean underground storm water drainage systems at 7-7 thru 7-23, and between buildings 3 and 7

(at six-month intervals)

Lizell Contracting $580 Operating 5/7/18
Temporarily relocate six (6) mailbox clusters and prepare concrete slab for new mailboxes Lizell Contracting $1,930 Operating 5/8/18
Turn off all boilers – M-1 thru M-25 Continental Property Management N/A N/A 5/10/18
Install baffles at soffit and four (4) box vents at roof – 2-7 Aspen Way Eiseman

Construction

$1,609 Operating 5/11/18
May gutter cleaning LFB Landscaping $650 Operating

GL “6522”

5/18/18
Removal of leaves/debris from inside all fenced-in above-ground oil tank locations Lizell Contracting $566 Operating

GL “6540”

5/18/18
Improve storm water drainage at front of 3-6 by installing Belgian block LFB Landscaping $225 Operating 5/22/18
Mid-summer gutter and downspout cleaning Bohley Enterprises $1,222 Operating 5/24/18