PROJECT | CONTRACTOR | ESTIMATED COST | FUNDING | COMPLETION DATE |
Replacement of electric sump
pumps in Boiler Rooms M-6, M-7, M-16, and M-23 |
Lizell Contracting | $1,864
($466/ Location) |
Operating
GL “6540” |
1/4/19 |
Replace sump pump battery at
M-16 (3-year cycle) |
Lizell Contracting | $300 (Est.) | Operating
GL “6540” |
1/5/19 |
Removal of leaves/debris from inside all trash enclosure areas | Lizell Contracting | Hourly rate | Operating | 1/7/19 |
Late-fall gutter and downspout cleaning | Bohley Enterprises | $1,692
(2017 Price $1,598) |
Operating | 1/10/19 |
Remove/dispose five old black metal mailbox clusters | Lizell Contracting | $560 | Operating | 1/11/19 |
Adjust maintenance fee for unit owners serviced by central boiler system – (if necessary, on a calendar basis) | Continental Property Management – after year-end balance sheet is published | Increased to $32/unit/cycle from $28/unit/cycle effective 2/12/19 | Operating
GL”5151” |
1/22/19 |
Schedule/confirm oil delivery by Brinker’s mid-cycle – January | Brinker’s Fuels | N/A | N/A | 1/24/19 |
Chip Christmas trees – install woodchip beds | LFB Landscaping | $700 | Operating | 1/31/19 |
2018 Financial Statement – Audit | Luft & Company, CPA | $2,100 | Operating | 2/4/19 |
Replace 3’ x 4’ concrete block and raise curb box at side of building 3, near M-9 | Genesis Concrete | $520 | Reserve | 2/5/19 |
Asphalt replacement at driveway at 8-7 – 3’ x 4’ | Peco Energy | N/A | N/A | 2/7/19 |
Extension to June 2018,Re-certification of boiler M-19 (required every two (2) years by PA Department of Labor/Industry) | Hartford Steam Boiler (Authorized by Nationwide Insurance) | $44 (2017 price) | Operating
GL “6540” |
2/7/19 |