COMPLETED PROJECTS
PROJECT | CONTRACTOR | ESTIMATED COST | FUNDING | COMPLETION DATE | ||
Remove branches/leaves/debris from roads, parking lot, roofs (from 8/4/20 tornado) | LFB Landscaping | $11,000 (submitted to insurance company) | Operating (Contingency GL “6590”) | 8/4/20 – 8/7/20 | ||
Removal of large branch that fell into building 1 requiring crane, and removal of large storm-damaged branches from roof, roads, and common area (from 8/4/20 tornado) | TreeEx | $22,760 (submitted to insurance company) | Operating (Contingency GL “6590”) | 8/4/20 – 8/7/20 | ||
Clean 25 boiler room chimneys | Doylestown Chimney Cleaning | $1,000 (2019 Price – $1,000) | Operating GL “6540” | 8/8/20 |