PROJECT CONTRACTOR ESTIMATED COST FUNDING COMPLETION DATE
Removal of leaves/debris from inside all trash enclosure areas Lizell Contracting Hourly Rate Operating 2/29/16
Lubricate locks at boiler room doors, M-1 through M-25, repair/replace as necessary Lizell Contracting Hourly Rate Operating

GL “6540”

3/2/16
Mail exterior building power washing letter to community Continental Property Management Copying &

Postage

Operating 3/4/16
Mail “Important Fire Safety Notice”, clean dryer ducts with first notice of annual election meeting Continental Property Management Copying &

Postage

Operating 3/7/16
Inspect 26 fire extinguishers in boiler rooms/ maintenance room (service at extra cost) Shapiro Fire

Protection

$400 Operating

GL “6540”

3/8/16
Tree removal and stump grinding at five (5) locations – From Council inspection Willow Tree $1,650 Operating 3/9/16
Re-install fallen “25 mph” sign near Aspen Way/Court Street PennDOT

(At Association Request)

N/A N/A 3/11/16
Turn on water to all exterior spigots at 25 boiler rooms and install hoses Lizell Contracting $175

(Approx.)

Operating 3/11/16
Lime turf application – pH 5.9 Bair’s Tree/ Lawn $780

(2015 Price – $780)

Operating 3/18/16
Exterior building power washing –

42 locations, 3,000 sq ft

Rolling Suds

( before installation of mulch)

$2,000

(2015 Price)

Operating 3/18/16
Power wash 35 trash enclosure areas

(all except 12-3) and notify residents in advance

Rolling Suds

(Before installation of mulch)

$3,200

(2015 Price –

$3,200)

Operating 3/18/16