PROJECT | CONTRACTOR | ESTIMATED COST | FUNDING | COMPLETION DATE |
Additional leaf clean-up (weather permitting) – before March
clean-up |
LFB Landscaping | $500 | Operating | 1/22/18 |
Schedule/confirm oil delivery by Brinker’s mid-cycle – January | Continental Property Management | N/A | N/A | 1/23/18 |
Maintain $28/unit/cycle maintenance fee for unit owners serviced by central boiler system | Continental Property Management | $28/month
per cycle |
Operating
GL “5151” |
1/23/18 |
Install three (3) LED floodlights facing Aspen Way at Buildings 3 and 7 | Frank’s Lighting | $2,451 | Operating | 1/23/18 |
Stucco repairs at 3-17 and 13-3 | John DePaul Masonry | $1,870 | Operating | 1/24/18 |
Replace batteries to sump pumps at boiler rooms M-10, M-23, and M-25 | Lizell Contracting | $804 | Operating
GL “6540” |
1/30/18 |
Chip Christmas trees – Install in wood chip beds | LFB Landscaping | $700 | Operating | 2/2/18 |
Tree removal and stump grinding – 14 trees (from 9/12/17 inspection) | TreeEx | $3,361 | Operating | 2/2/18 |
Improve storm water drainage at sidewalk at front of 1-3 / 1-4 | LFB Landscaping | $1,200 | Operating | 2/2/18 |
2017 financial report
(audit required by documents) |
Luft &
Company |
$2,100 | Operating | 2/4/18 |
Install 10-foot signpost and replace damaged “stop” sign at Aspen Way/Lower State Road | HD Supply
(Purchase)
Lizell Contracting |
$397
Hourly Rate |
Operating | 2/5/18 |
Mold remediation in common area attic above 2-7 | Environmental
Mold Solutions |
$2,480 | Operating | 2/9/18 |
Remove oak tree and grind stump at side of 8-8 | TreeEx | $1,080 | Operating | 2/12/18 |