COMPLETED PROJECTS

PROJECT CONTRACTOR ESTIMATED COST FUNDING COMPLETION DATE
Removal of leaves/debris from inside all trash enclosure areas Lizell Contracting $838 Operating 12/18/19
Spread one pile of woodchips at inbound lane of Aspen Way across from Building 3 LFB Landscaping Hourly Rate Operating 1/10/20
Additional leaf clean-up (weather permitting) – before scheduled March clean-up per contract LFB Landscaping $500 Operating 1/10/20
Community-wide tree pruning – according to detailed specifications Davey Tree $5,320 Operating 1/15/20
Schedule/confirm oil delivery by Brinker’s mid-cycle – January Continental Property Management N/A N/A 1/21/20