COMPLETED PROJECTS
PROJECT | CONTRACTOR | ESTIMATED COST | FUNDING | COMPLETION DATE |
Remove large storm-damaged tree branch at building 3 and Aspen Way | TreeEx | $166 | Operating | 6/5/20 |
Replace twenty-three (23) remote oil timers at M-16, M-17, M-19, and M-20 | Frank’s Lighting | $4,321 | Operating “GL 6540” | 6/9/20 |
Install summer annuals at selected mulch beds | Council | To Be Determined | Operating | 6/15/20 |
Removal of leaves/debris from inside all fenced-in above-ground oil tank locations | Lizell Contracting | $617 | Operating GL “6540” | 6/17/20 |
June gutter cleaning | LFB Landscaping | $650 | Operating GL “6522” | 6/22/20 |